Install the seals

  1. Cut 58 mm (2 5/16 in) off the top of the seal at one end.
  2. Install the seal to the U-profile on the right side of the pod from the ceiling to the floor.
    Note: Start the installation with the end where the top is cut off at the edge of the fold in the ceiling felt.
  3. Cut the seal at the floor end.
  4. Cut 40 mm (1 9/16 in) off the top of the seal.
  5. Install the other half of the seal to the U-profile on the left side of the pod from the ceiling to the floor.
    Note: Start the installation with the end where the top is cut off.
    Note: Press the DC extension cord into the seal.
    Note: If you installed the power cord from the roof, press the power cord into the seal.
  6. Lift the table into the pod and against the left side wall.
    Note: Make sure that the DC extension cord and the seal are not pinched under the base plate of the table.
  7. Cut a small slit vertically and another horizontally in the seal under the wall bracket.
    Note: Make sure that the DC extension cord is not cut or damaged.
  8. Pull the seal out of the U-profile.
  9. Guide the DC extension cord through the slit.
    Note: If you have installed the power cord from the roof, guide the power cord through the slit.
  10. Press the seal back into the U-profile.
  11. Cut the seal to the correct length.
    Note: Measure the seal to the floor.
  12. Cut 40 mm (1 9/16 in) off the top of the seal.